This page last changed on Mar 29, 2011 by kgomes.
Attendees
  1. Chris Grech
  2. Charlie Paull
  3. Peter Brewer
  4. Doug Au
  5. Kevin Gomes
  6. Annette Gough
  7. Aaron Greg
  8. Bruce Robison
  9. Mike Pinto
  10. Steve Etchemendy
Notes
  1. nov 30 point lobos will be shutdown and put up for sale
  2. 58 flyer days after GOC
  3. April 18 to may 18 transit to ML
  4. June we will have schedule for 2012 project
  5. July stability review by Glosten
  6. December shipyard for equipment installation
  7. early 2012 and during GOC we will have infrastructure
  8. \\tornado\DMO\coastalvessel is where documents are located
Document generated by Confluence on Feb 03, 2026 16:22